NANDHA GROUPS

S&T contractor

🚦 S&T Work Flow — Railway Projects

Pre-Execution Stage (Planning & Preparation)

Pre-Execution Stage (Planning & Preparation)

Before starting work, all permissions and materials are arranged.

Key Activities:

  • Site Survey & Route Inspection
  • Identify station layout, cable routes, signal/point locations.
  • Collect approved SIP and Cable Route Plan.
  • Material Verification (RDSO-approved materials).
  • Site Office & Storage Setup.
  • Coordination Meetings with departments.
Drwaings

Drwaings

Railway technical drawings using CAD software and printed plans.

Key Activities:

  • Signal interlocking plan
  • Cable core plan
  • Cable route plan
  • Track bonding plan
  • Point circuit diagram
  • Key lock circuit plan
  • Signal wiring diagram
  • Shunt signal diagram
  • Track circuit equipment layout
  • Power drawing
  • FTOT Diagram ( particulars )
  • Location ( Particulars )
  • Location circuit Diagram
  • Floor plan ( Optional )
Foundation & Civil Works

Foundation & Civil Works

Civil preparation for mounting of signalling and telecom equipment.

Key Activities:

  • Signal post foundations (CC 1:2:4 / 1:3:6).
  • Location box bases, point machine foundation with GI pipe route.
  • Cable trench excavation and sand cushioning.
  • Route marker stone fixing.

Documents:

  • Foundation register
  • Cable route sketch
Cable Laying & Termination

Cable Laying & Termination

The backbone of S&T systems — signal, point, and telecom connections.

Key Activities:

  • Laying of Signaling Cables: 10C / 19C / 24C
  • Telecom Cable / OFC Laying.
  • Cable Termination in location & relay room.
  • Insulation & Megger Testing.

Documents:

  • Cable Megger Report
  • Cable Route Documentation
Installation of Equipment

Installation of Equipment

Now the actual devices are installed and wired for signalling, telecom, and power.

Key Activities:

  • Color light signals, point machines, track circuits.
  • Relays & panels in relay room.
  • Telecom: exchanges, PA system, block instruments.
  • Power Supply: IPS, DC-DC converter, earthing, surge protection.
Wiring & Interlocking

Wiring & Interlocking

Ensures system logic is safe and correct as per approved SIP.

Key Activities:

  • Wiring between relays, panels, and field equipment.
  • Interlocking logic verification.
  • Continuity and relay contact tests.
  • Proper tag marking and documentation.
Testing & Commissioning

Testing & Commissioning

Testing is done by authorized railway S&T officials under strict supervision.

Key Activities:

  • Signal Aspect Testing, Point Operation, Track Circuit Working.
  • Cable IR & Continuity Check.
  • Voltage Drop & Functional Test with Panel.
  • Joint inspection and commissioning.

Documents:

  • Signal sighting certificate
  • Provisional acceptance report
Documentation & Handover

Documentation & Handover

After successful testing, documents are prepared and handed over to the Railway.

Key Activities:

  • Cable route plan (as executed).
  • Wiring diagram (as executed).
  • Megger & testing reports.
  • Material utilization record.
  • Safety & completion certificate.
Call Now